New quay and sea defences at the heart of Lajes das Flores port rebuild

The rebuilding of Lajes das Flores port had reached €42.7 million in spending by June 2026, out of an overall planned investment of €191.5 million.

Construction of the new port at Lajes das Flores had recorded €42.7 million in expenditure by the end of June 2026, against a planned investment of €191.5 million. The project is intended to rebuild and strengthen infrastructure essential to the island after damage caused by Hurricane Lorenzo.

The figures appear in a report on recovery from the hurricane, submitted by the Azores Government to the Regional Legislative Assembly. Of the €42.7 million, €14.5 million had been spent by the end of 2025 and a further €28.2 million during the first six months of 2026.

The plans include extending the breakwater protection by 95 metres and building a new pier and quay with 170 metres of berthing length and a width of 40 metres. They also provide for dredging near the quay, a port operations support building and work on the port's technical networks.

The construction contract was formally handed over on 17 April 2025, following its signature in March that year, and has a 60-month execution period. The report prepared by Portos dos Açores tracks both the physical and financial progress of the recovery work.

For Flores, the project is a step towards restoring operating conditions at a port that plays an essential role on the island. According to the Regional Government, it is also the principal intervention in the rebuilding of port infrastructure affected by Lorenzo in the Azores.